Warrina Valley development

Site Visits during Construction

 

2nd July 2002

Weather is having its usual seasonal variations. Today was pleasant, sunny, but chilly and dry, which made site inspection a delight. The builders had really pulled out all stops, with nos 16 and 17 being fully clad on all internal walls, and No.16 having the bulk of the built-in cupboards fitted, which made a vast difference to the look.

Indeed the internal finish drew gasps of surprise from several as-yet uncommitted visitors to the site who were inspecting our house, and perhaps some of the few remaining houses to be allocated will go shortly.

Various internal shots were taken for comparison with the previous week; by and large work in progress showed a large amount of framework constructed on slabs towards to road, on the southern side, but there are still foundations to be dug on the blocks previously covered by Mount Sinai along the northern boundary where the creek runs.

 

Something that appears to have happened ahead of schedule is the foundations for the Community Centre; we got two good shots, one from the North-East; the second shot, taken from the South-West, is shown with the images shot the next visit.

 

Two days earlier I had photographed (through the chain link fence) the now cleared area just south of the creek, waiting for foundations to be dug for houses 30 to 34. While I was there I took a snap from Reservoir Road of the grossly overgrown creek which forms the northern boundary of the property.

,

 

16th July 2002

It has bucketted down with rain for nearly ten days... Here we see two days before (14th July) at midday, trucks parked with trays raised to let the water out) and a pool still on the ground, photo shot at midday!

.

The tradesmen on site have been busy with other houses less advanced, but we can see that the rendering of the columns outside has been finished. To the right is a shot of the recently poured but unfinished Community Centre slab shot from the SW corner.

.
Had the weather not been so wet, it is likely that some painting might have been done.

 

30th July 2002

It continued to rain for a bit, but eased for a few days before the resident visit. Again we see two days before (28th July) in the afternoon, progress on the roadside allotments, with the slabs for numbers 30 to 34 having been poured.

.

The northern boundary of the property starts to take shape

And some shots of the Community Centre, which is just framework at this stage - and indeed for another month afterwards. On the left we see the exterior view from the front, and on the right we are standing at the eastern corner of the Hall looking ahead at the chapel alcove, and to the right toward the servery that is part of the kitchen beyond.
.

 

13th August 2002

The week before the visit (5th August) shows progress on houses 30 to 34 well in hand.

..

We didn't take any general photos today;
there were only two exposures left on the Advantix camera - which we used on our own house.

Nov-Dec 2001 - Jan-Feb 2002 - Mar-Apr 2002 - May 2002 - June 2002 - July-Aug 2002
Aug-Sep 2002 - Oct 2002 - Nov-Dec 2002 - Jan-Feb 2003 - Mar-Apr 2003 - Community Centre

Created 10th December 2002